Main tile laid

The tile in the main room of the Under Hill Suite is all laid, save for the small accent tile under the kitchen counter area and around the stove. The plumber installed the toilet and taps, taking things one step closer to the open house scheduled for June 7. We are getting more excited each day.

Grout!

The plumber is the next trade due to arrive to install the taps, sinks, and fixtures, which means the tile work needs to be finished. Julianne and Peter trowelled on the dark mud, and after it had set, they began sponging off the excess. It looks every bit as spectacular as we hoped it would. There are only forty-four days until the Yarrow Days open house!

Down to the wire

With only forty-five days until the June 7 open house for the Under Hill Suite of the Hazelnut Inn, we are down to the small details. Our friends from BNR Electric are busy installing the final fixtures and switches. They also took the time to hook up the outdoor gas fireplace, which our guests will surely enjoy.