A day of progress and adventure.

Now that the concrete is poured into the lower walls of our house it is time to backfill around the outside and bury most of the walls inside as well in order to bring the floor level up to what the city required. We will use a coase sand on the inside as it packs well and is easy for the plumber to dig the trenches he needs for the plumbing. We will need about 500 cubic yards of material for the task. We got seven loads of sand delivered before the road was closed between our place and the gravel pit because of an accident. More sand will come tomorrow.

As I put the fill into the carport area I quickly learned how tricky operating a bobcat can be and how quickly things can go suddenly awry. I got a little close to the edge and in an instant slid precariously into a post leaning the bobcat dangerously towards an area not yet filled. I knew ell enough to stop before I made things worse. It took a whole lot of head scratching, a plan of action and some strong pulls with the pickup to get things back on track. Bobcats are HEAVY machines! I learned my lesson about soft edges and bobcats real well. No pictures were taken during the adventure. Only one scoop of sand actually got dumped inside the foundation before we ran out of material.

driveway filled in.png

Since the sand supply had dried up we kept working on other things. We had trasplanted five small trees from beside our driveway to make room for a new parking area near the new house. I prepared the ground and then put in the gravel to raise that area to match the elevated driveway.

rearranged entry.png

Out by the shop Haley and Peter were working on the window bucks and making good progress (when they weren't trying to get a bobcat unstuck). Most of the smaller windows are now done and ready to install into the LOGIX forms as we stack them up. These bucks will act as forms for the concrete we pour inside.

window bucks 1.png
window bucks 2.png

It was a great day of progress with enough adventure to make it memorable.

-grampa dan

Second pour

Today was the second concrete pour for our house. The LOGIX ICF (insulated concrete forms) were stacked four high, to 54" tall, bringing the walls about 12" above the final finished floor. Harold and his crew did the bulk of the work on this pour.

concrete pumper 1.png
pumper 3.png

Here's a shot of Colin who got more splattered by the concrete than anyone else on the crew.

colin covered in concrete.png

We used 39 cubic meters (51 cubic yards) today. This brings to total volume of concrete to 47 cubic meters (74.5 cubic yards) so far. Tomorrow we'll begin filling the inside of the foundation with course sand. For that task I borrowed my neighbor Gord's bobcat. I haven't operated a bobcat for many, many years. I practiced my manouvering by moving a huge pile of dirt which will be used for backfill to the front yard. It took me about three hours. By the end of that time I had gotten a little smoother at the contols but I was so stiff and sore from all the bouncing and jostling I recieved. I was reminded why a bobcat is not my favorite machine. I also learned it is best to wait at least an hour after eating to use such a machine.  :)

bobcat.png

Tomorrow we'll begin with the sand inside the foundation.

-grampa dan

Crazy day!

Today started nice and mellow. It wouldn't stay that way for very long. Harold's crew worked on making sure the first few rows of the LOGIX forms were perfectly level. I went to get another load for them to stack on top. When I got back to the worksite the fellow who was installing the septic tanks had arrived along with his excavator and a giant truck with the massive precast concrete tanks. From that point on the worksite was wall to wall action. A second hiab truck arrived with the rented forms for the inside bearing walls. Pharm dug a neat hole and they coaxed the tank into place without bumping the footing posts for the porch.

tank in.png

I had meetings with clients, and ran a number of trips for the last of the LOGIX blocks. A short while later both tanks were in place.

both tanks in.png

By the end of the day most of the required block for the first pour was in place. It was starting to look like a house construction site at last.

end of day.png
blocks from east side.png

We'll be pouring the first four rows of blocks on Thursday. Following that it will take a few days to place the many, many truckloads of sand inside the foundation, packing it firmly into place as we work our way to the top. We'll also do much of the backfilling on the outside of the foundation at the same time. Then we'll begin stacking the LOGIX blocks the rest of the way up to the ceiling hieght and do one more pour to finish the walls. In about two weeks it will be time to begin setting the roof trusses into position. 

Many folks are stopping by, amazed at the quick progress... but I'm trying my best to figure out ways to make it all go faster. Christmas is coming fast and it is our hope to be in the house by then.

-grampa dan