Assembling the LOGIX blocks

Today was the first day of putting down the LOGIX blocks. Harold's crew took great care to first layout a perfectly square and accurate building onto the footings. Once all the chalk lines were snapped it was time to begin placing the LOGIX blocks. They bottom row was laid out and then tied togeher with nylon straps, always starting at the corners. Here Colin is tying the corner blocks of the entry.

first blocks on foundation.png
colin tying blocks.png

Heavy rebar was then snapped into place before the next row was fit on top. The second row was tied together and also to the first row. The crew then used a laser level to make sure everything was perfect. The blocks were shimmed as necessary and then glued to the footings using a low expansion spray foam. By the end of the day they had completed two full rows. It will go faster from this point as there will be a lot less tying of blocks necessary. Four rows of blocks will be placed before the first pour. We can then fill the inside of the foundation with sand to seven inches below where the concrete floor will be poured. We should be ready to pour the first stage of the walls on Wednesday.

-grampa dan

Something new is afoot.

Today when I peeked out of the curtains this morning at 6:30 am the concrete pumper truck was pulling up in front. No time for breakfast today! We had the massive truck positioned and set up in a hurry and the first concrete truck pulled up at 7:00 am sharp!

concrete trucks.png

The pour went quick and without incident. (Always a good thing with concrete.) By coffee time the concrete was in place and largley done. The footings for the new house were DONE!

pouring footings.png

Instead of the usual sono-tubes we used the new Fast-tube  www.fab-form They worked pretty cool and were easy and quick to set up.

With most of the land forming now roughly in place it was time to put up the contractor and supplier signs. There will be more added in the next days.

It was a great day! Tomorrow the LOGIX walls wil be started to be set in place. It is starting to look like a house!

-grampa dan

Raising the roof (and floor)

Today was a busy day as we checked and double checked everything in readiness for the concrete pour first thing tomorrow.  The city building inspector came for a look and also told us (at last) the required height of the floor of our house. Because we live on a flood plain we have to build up the land considerably. 

ready for concrete.png

The view should be pretty good from way up there.

-grampa dan