BIG day!

Today was at last the day when the walls of our new house would be poured with concrete - right up to the rafters. The concrete is eight inches thick, providing a big thermal mass. Heavy rebar that is sixteen inches on center each way will provide the strength. The three and a half inches of foam on each side of the concrete will provide the insulation to keep us warm in the winter and cool in the summer. Plastic webs that go through the concrete and into the LOGIX foam on each side at eight inches on center will be the secure attachment points for interior and exterior finishes and trim. 

Weeks of hard work and preparation would at last be rewarded. 

When I came out of the door just before seven AM the PSI pumper truck was idling at the curb. We positioned him into the driveway and set out his outriggers to maintain balance when we reached out more than one hundred and thirty feet to fill the far corners of the house walls. Right on time (at 7:30 AM) the Western Concrete truck pulled up with the first of five loads of concrete. We would place a little more than sixty cubic yards of concrete in the next six hours.

trucks arrive.png

While the trucks set up our crew did one last check of the forms and set out their tools in preparation. Excitement was high and everyone was eager to get started. The concrete would be poured in lifts around and around the walls until we reached the top. The first lift would be just past the bottom of the windows.

pumper truck in action.png
filling back gable.png
filling front gable.png
filling forms.png

Time flew by and it didn't seem long until the nine foot tall walls were full of concrete. While Harold's crew made sure everything was perfectly level and straight, I trowelled off the top edge and set the anchor bolts for the top plates that would hold the trusses. The steeply angled gable ends took a little longer to fill but by one o'clock the concrete was where it was supposed to be without incident. Harold's Conctracting crew performed like a well oiled machine. The concrete mix from Western concrete was consistent and perfectly mixed. The driver from PSI pumping was smooth and capable. My crew handled all the little chores and details to allow everyone else to keep focused on their task. It all made for a perfect pour. The training we recieved from Patick Chan of LOGIX ICF a few weeks ago proved to be valuable and the many tips he provided made the job go smoother without a doubt. THANKS to all involved for a massive effort and a very successful day!

-grampa dan

More signs

Many of the contractors and suppliers for our new house have signs out front to advertise their participation. They were selected only after lots of research and we are very proud to have them a part of our project. But we asked they not display the typical coroplast signs on our project. The signs displayed had to be of the same quality that we do on a regular basis. We made each of them a dimensional version of their logo. They will get to keep the sign when the project is done.

sarah painting penhold's sign.png
peter welds signs to base.png
signs.png

More signs are being added on a regular basis as we bring more folks on board.

-grampa dan

READY!

Today dawned rainy and wet but the crews were eager to get going. Today was the day before the biggest concrete pour of the project. Today we were to make sure everything was totally ready and we were committed to stay until everything was perfect. Concrete waits for no one.

The crew worked hard but spirits were high. Weeks of preparation was done and they had done a great job. 

As I went by our rooster out front I noticed he was wearing some special gear in spirit of the project underway.

safety rooster 2.png
safety rooster.png

Bracing was going up everywhere, including the front door, making everyone crouch down as they entered or left the building. I wrote a note on the cross board advising everyone to DUCK! Someone else added the second notation.

duck goose.png

Elsewhere on the site everyone was busy adding bracing, securing loose bits and making sure everything was nice and level. The upper gables had to be capped to allow them to be filled with concrete to the very top.

guys high on scaffold.png
door side of the house.png
scaffold on front wall.png

Thanks to everyone's hard work we were ready... almost.

house ready for pour.png

We had one more detail to take care of in preparation for the theme work that will soon begin. Peter drilled holes in the foam forms and inserted steel rods into the interior. These short steel rods would be used to weld the armatures of the trees that would flank the big windows and the front door.

peter putting in tree anchors.png
front door rebar.png

Now it is time to rest until early tomorrow when the real fun starts. It is almost concrete day.

-grampa dan